Claranet blames data centre for downtime

Global Switch fingered

Claranet has blamed data centre Global Switch for a power failure early this morning which brought down many of its customers' websites.

The problem was caused by a power failure at Global Switch 2 in London - its purpose-built data centre which claims two independent power supplies. The company boasts that it's Europe's biggest purpose-built centre.

Claranet, which apologised to customers hit by the downtime, said two routers went down as a result of the power failure. Its engineers are still monitoring the problem, although power has been restored.

Claranet said:

The problem was with Global Switch and the issue was resolved as follows:
  • 2:54 AM - power issue
  • 3.30 AM power restored to GS2 overall
  • 3.50 AM power restored to all Claranet customers in GS2 and began checking customer specific services

Global Switch was unable to comment. ®

Free Download - The Reg Guide to Extended Validation

Don’t Miss

email symbolStill sending naked email? Get your protection here

Security How-to Buckle your seatbelt, encrypt your bits

Google's Satan phoneT-Mobile G1 Google Android-based smartphone

Review Operating System 1, Hardware 0

Ubuntu teaser Ubuntu 8.10 - All Hail new Network Manager

Review The good kind of UI theft

OpenOffice_logoOpenOffice 3.0 - the only option for masochistic Linux users

Review And linear optimizing Mactards