US Government Accountability Office dumps sack of coal on NASA's desk over Moon mission naughtiness

It'll be fine, just keep giving Boeing money


Those within NASA hoping for some festive treats were in for disappointment this week as the US Government Accountability Office (GAO) administered a kicking over the agency's beleaguered Artemis programme.

The GAO's report spelled out just how much trouble the over-budget and behind-schedule Moon mission is in, and remarked that things hadn't really improved since its last report in 2019.

Noting that the first launch of NASA's heavy launcher, for the uncrewed Artemis I mission, "was again delayed, this time due in part to manufacturing challenges," the GAO pointed out that "the new date, November 2021, doesn't take into account any COVID-19 delays."

To put that postponement into context, NASA put in place a schedule to measure performance in 2014. Since then, according to GAO, Artemis I has suffered a 36-month slip. Even the latest launch date (November 2021) might be in doubt due to problems including an issue with the Orion capsule and the impact of COVID-19 on the programme.

The delays to Artemis I will have a direct impact on Artemis II. Bits of the Orion crew module of Artemis I are planned for Artemis II, but refurbishment and installation will take "a minimum of 20 months" meaning the earliest Artemis II could launch would be July 2023. That would mean only 14 months until the Moon landing mission of Artemis III, scheduled for September 2024.

It's all starting to look rather tight, and one can't but help wonder if an incoming US administration might opt to fiddle with the boots-on-Moon-soonest approach of Donald Trump in favour of something a little more sustainable and, dare we say it, achievable.

Costs have also continued to rise. The SLS programme has jumped by 42.5 per cent and the Exploration Ground Systems (EGS) by 32.3 per cent since 2014, according to the GAO. An overall increase of $3bn to $11.5bn, and more revised estimates are due in 2021.

A sizeable chunk of cash has been spent on missions beyond Artemis I, but a lack of focus after Artemis I and the crewed Artemis II by the agency "places billions of dollars at risk of insufficient NASA oversight," according to the GAO.

Indeed, the report reads as though NASA had assembled a set of dominos, with a delay in Green Run testing of the SLS core stage impacting Artemis I, which impacts Artemis II and so on. Sadly, for folk fondly remembering the epic domino runs of old, the only record broken is likely to be in the budget overrun arena. And that's without considering the more powerful versions of the SLS needed for missions after Artemis III.

The GAO did note the progress being made by NASA, but commented: "This progress has also been accompanied by extensive cost overruns and schedule delays for the SLS, Orion, and EGS programs."

"NASA," it added, "is also facing further risks as it begins to commit billions of dollars to the development of future capability upgrades for these programs while mission requirements remain in flux."

Sounding a little like a broken record, the GAO recommended the agency establish cost and schedule baselines for the next round of Artemis and SLS work, as well as adding technical performance updates in its quarterly status reviews.

For its part, NASA concurred with the recommendations and set an estimated completion date of 31 March 2021 for the latter and 30 September 2021 for the former. ®

Similar topics


Other stories you might like

  • NASA to commission independent UFO study
    The truth is out there, and the space agency intends to find it – scientifically

    Over recent years, Uncle Sam has loosened its tight-lipped if not dismissive stance on UFOs, or "unidentified aerial phenomena", lest anyone think we're talking about aliens. Now, NASA is the latest body to get in on the act.

    In a statement released June 9, the space agency announced it would be commissioning a study team, starting work in the fall, to examine unidentified aerial phenomena or UAPs, which it defined as "observations of events in the sky that cannot be identified as aircraft or known natural phenomena."

    NASA emphasized that the study would be from a "scientific perspective" – because "that's what we do" – and focus on "identifying available data, how best to collect future data, and how NASA can use that data to move the scientific understanding of UAPs forward."

    Continue reading
  • Meteoroid hits main mirror on James Webb Space Telescope
    Impact at the end of May bad enough to garble data, but NASA isn't worried

    The James Webb Space Telescope has barely had a chance to get to work, and it's already taken a micrometeoroid to its sensitive primary mirror.

    The NASA-built space observatory reached its final destination, the L2 orbit, a million miles away from Earth, at the end of January.

    In a statement, NASA said the impact happened some time at the end of May. Despite the impact being larger than any that NASA modeled and "beyond what the team could have tested on the ground," the space agency said the telescope continues to perform at higher-than-expected levels. The telescope has been hit on four previous occasions since launch.

    Continue reading
  • Astra fails, sends NASA's Tropics weather satellites back to Earth
    Orbital success counter stuck at 2 as upper stage of rocket shuts down early and CubeSats lost

    The first of NASA's TROPICS constellation launches came to an unscheduled end over the weekend as the Astra launch vehicle it was riding failed to deliver the cubesats to orbit.

    It was all going so well. The two cubesats lifted off atop an Astra Rocket 3 from Space Launch Complex 46 at approximately 1343 EDT on June 12, 2022.

    The initial flight seemed go swimmingly, but things went wrong after the first stage had completed. Viewers of video streaming live from the rocket saw what appeared to be the start of some tumbling before the feed was abruptly cut off. NASA's California-based commercial rocket-making partner Astra confirmed that the upper stage had shut down early, dooming the payload to a considerably earlier than planned rendezvous with Earth.

    Continue reading
  • Former chip research professor jailed for not disclosing Chinese patents
    This is how Beijing illegally accesses US tech, say Feds

    The former director of the University of Arkansas’ High Density Electronics Center, a research facility that specialises in electronic packaging and multichip technology, has been jailed for a year for failing to disclose Chinese patents for his inventions.

    Professor Simon Saw-Teong Ang was in 2020 indicted for wire fraud and passport fraud, with the charges arising from what the US Department of Justice described as a failure to disclose “ties to companies and institutions in China” to the University of Arkansas or to the US government agencies for which the High Density Electronics Center conducted research under contract.

    At the time of the indictment, then assistant attorney general for national security John C. Demers described Ang’s actions as “a hallmark of the China’s targeting of research and academic collaborations within the United States in order to obtain U.S. technology illegally.” The DoJ statement about the indictment said Ang’s actions had negatively impacted NASA and the US Air Force.

    Continue reading
  • Mars helicopter needs patch to fly again after sensor failure
    NASA engineers continue to show Ingenuity as uplinking process begins

    The Mars Ingenuity helicopter is in need of a patch to work around a failed sensor before another flight can be attempted.

    The helicopter's inclinometer failed during a recommissioning effort ahead of the 29th flight. The sensor is critical as it will reposition the craft nearer to the Perseverance rover for communication purposes.

    Although not required during flight, the inclinometer (which consists of two accelerometers) is used to measure gravity prior to spin-up and takeoff. "The direction of the sensed gravity is used to determine how Ingenuity is oriented relative to the downward direction," said Håvard Grip, Ingenuity Mars Helicopter chief pilot.

    Continue reading
  • Algorithm spots 104 asteroids in huge piles of data
    Rocks stood out like a THOR thumb for code

    Researchers at The Asteroid Institute have developed a way to locate previously unknown asteroids in astronomical data, and all it took was a massive amount of cloud computing power to do it.

    Traditionally, asteroid spotters would have to build so-called tracklets of multiple night sky images taken in short succession that show a suspected minor planetoid's movement. If what's observed matches orbital calculations, congratulations: it's an asteroid. 

    Asteroid Institute scientists are finding a way around that time sink with a novel algorithm called Tracklet-less Heliocentric Orbit Recovery, or THOR, that can comb through mountains of data, make orbital predictions, transform sky images, and match it to other data points to establish asteroid identity.

    Continue reading

Biting the hand that feeds IT © 1998–2022